    Hi HelpMasters,

    We are currently in the process of creating new reports for the next release of HelpMaster.  The new reports will display details about reponse times / sla's / time periods etc. 

    In order to create the most useful reports, we are seeking some feedback on the topic of response times.

    How do you define response time?

    1. Is it the date / time when you acknowledge the job (using the dedicated "Acknowledge job" action button?
    2. Is it the first staff action after the initial log job action?
    3. Is it when a job enters a particular job status?
    4. When a job gets re-assigned - a popular one when all jobs are initially logged and assigned to a skillgroup, or other "pool" of jobs.
    5. ...or something else?

    Looking forward to your response and ideas for some great "Response time" reports.

    Rod

    HelpMaster development team
    Check out the HelpMaster roadmap
    Russ
    New Member
    New Member
    Posts:8
    Points:8


    --
    03/24/2011 4:43 AM
    I saw this post and couldn't help but respond... :-)

    I've found in the past that "response times" can be a very contentious issue. But my take on this is that it must be from the customer's perspective of how the question is being progressed, so I say the customer see's the "first response" as the first steps towards resolution (a suggestion, request for more information, etc) and not just confirmation that the call has been logged and has an associated reference.

    Too often auto-responders are used as the measure of whether first response SLA's have been met; but from a service perspective, the customer hasn't received anything yet.

    Any thoughts, anyone ? :-)
    Timo de leeuw
    Helpdesker
    Helpdesker
    Posts:13
    Points:19


    --
    03/24/2011 5:03 AM
    I would agree with Russ. We have used Acknowledge in the past but it was with various success. The way we have the templates set up it can be easier to use another another action type to update the client (such as request for further information) but then you do not get the right date/time stamp as per acknowledge. You then end up either using the ack option and add the other detail to that action such as email templates etc or you end up doing both.
    For this reason we went away from using this.

    My vote also would be the first action be it a status change or notes update. The only thing I would exclude is the reassigning of a job. When I reassign I move the ownership but this does not mean that anything has happened or the customer has been updated.
    Rod Weir
    HelpMaster development team
    Helpdesk Hall of Fame
    Helpdesk Hall of Fame
    Posts:538
    Points:968


    --
    03/24/2011 7:23 AM
    Hi Russ and Timo, thanks for your input. This is good feedback.

    Sounds like both of these preferred measures of response time can be pinpointed by reporting on the first time is placed into a specific job status.

    A best-practice that we suggest with HelpMaster (or any helpdesk system) is to use an "us and them" naming convention for job status. To use a tennis analogy, when the ball (job) is in the clients' court, the job status reflects something like "Client : Awaiting response". When they do respond, the job status changes to "Staff : Awaiting response" or similar.

    So what I'm getting from your feedback is that a good definition of response is when the client is actually contacted by someone at the helpdesk / service desk etc. In the example above, it would be the first time the job status is changed to a job status like "Client : Awaiting response" or similar.

    Perhaps a future HelpMaster improvement / feature could be to mark certain job statuses as being the trigger for a response?

    Another other ideas?
    Rod

    p.s. Russ - great to hear from you again.

    HelpMaster development team
    Check out the HelpMaster roadmap
    Timo de leeuw
    Helpdesker
    Helpdesker
    Posts:13
    Points:19


    --
    03/24/2011 9:23 AM
    We picked up the "us and them" approach from this website a while ago and have been using it ever since. One of those simple but effective ideas.

    As to the question though. When we log the job is is set to "0. Open Issue" and so in other words nothing has happened on it yet. The next step could be one of two mainly.
    "AB: Work in Progress" - we have started to work on it
    "Client: Awaiting Customer Response" - we have requested more information or we could have provided the solution and just awaiting confirmation. in this was then it incorporates the WIP status and the ACR status in one.

    so a status change would be good to have as the trigger but it may not be any specific status listing.

    Hope this helps
    Russ
    New Member
    New Member
    Posts:8
    Points:8


    --
    03/24/2011 9:42 AM
    I would agree with "the two state" persepctive... we're either doing something or waiting for something... although, in our present circumstances, we have a 3rd party, the app. vendor (to show as a location, not so much a status change), when coding issues need to go "back to base." (and we need to account for 3rd party SLA's)

    But to continue the tennis analogy, we occasionally have to refer to Hawk Eye when someone shouts "Out !!" (Maybe HMP could throw out some chalk dust... :-)

    We would entirely agree with Rod above, that a response is "when the client is actually contacted by someone..."

    Triggers driven by status is a great idea. And when linked to age, or time progress against SLA for that priority, this provides the customer with assurances that work is happening, without them needing to chase... which means less interruptions, less escalations... and so we all lived happily ever after... :-)

    Timo de leeuw
    Helpdesker
    Helpdesker
    Posts:13
    Points:19


    --
    03/24/2011 9:49 AM
    Just had another thought. Would it be possible to set the SLA based on the priority. Currently when we log jobs we assign a priority ( / impact state).
    It would also be good if we could set the associated SLA again the system code. So if then I select a P3 then the system would already know (and notify) that it needs to be done within 2 days, if it is a P4 then it would give it 5 days.

    Currently the only way I can see i can do this is by setting the Time Option "set the 'To be completed by' date to be in ..." within the job template. This is ok but not great as then I have to set up a job template for each priority which in the end is counter productive.

    Is it possible?
    Rod Weir
    HelpMaster development team
    Helpdesk Hall of Fame
    Helpdesk Hall of Fame
    Posts:538
    Points:968


    --
    03/24/2011 6:20 PM
    Hi Timo,

    If you need to set the "To be completely by" date in the job, you can use the Priority Manager to do it for you. See http://www.helpmasterpro....n-Board/aft/292.aspx

    Once this date has been set, you can then create another Priority Manager profile to send the SLA notification emails and breach warning etc. See http://www.helpmasterpro....on-Board/aft/39.aspx

    We are also considering a major enhancement to the Priority / SLA / To be complete by feature for an upcoming version of HelpMaster that will be largely driven by the priority of the job.

    Hope this helps,
    Rod
    HelpMaster development team
    Check out the HelpMaster roadmap
    You are not authorized to post a reply.


    Allow staff to view all jobs, all skillgroups by Rod Weir in Installation, configuration and upgrading with 0 replies By default, staff members can only view and action jobs that are assigned to the skillgroup(s) that the staff member belong to.  Fine-level contr...

    Building knowledge management and KCS into the workflow by Rod Weir in Using HelpMaster with 0 replies Here's a workflow idea to assist with improved knowledge base articles and knowledge management / KCS As part of a support workflow, build into...

    June 2019 release now available by Rod Weir in Announcements with 0 replies A new release of HelpMaster is now available.  This release builds upon features and stability, particularly in the workflow, and change manageme...

    Workflow email object - email account by Rod Weir in Using HelpMaster with 0 replies The up-coming release of HelpMaster will have a lot of workflow improvements.  One of these is in the email object.  It is now possible to c...

    Change Management by Rod Weir in Using HelpMaster with 0 replies Change Management in HelpMaster is a relatively new feature that is evolving rapidly.  Based off live-use in small and large departments, our &qu...

    Allow staff to view all jobs, all skillgroups by Rod Weir in Installation, configuration and upgrading By default, staff members can only view and action jobs that are assigned to the skillgroup(s) that the staff member belong to.  Fine-level contr...

    Building knowledge management and KCS into the workflow by Rod Weir in Using HelpMaster Here's a workflow idea to assist with improved knowledge base articles and knowledge management / KCS As part of a support workflow, build into...

    June 2019 release now available by Rod Weir in Announcements A new release of HelpMaster is now available.  This release builds upon features and stability, particularly in the workflow, and change manageme...

    Workflow email object - email account by Rod Weir in Using HelpMaster The up-coming release of HelpMaster will have a lot of workflow improvements.  One of these is in the email object.  It is now possible to c...

    Change Management by Rod Weir in Using HelpMaster Change Management in HelpMaster is a relatively new feature that is evolving rapidly.  Based off live-use in small and large departments, our &qu...

    April 2019 release now available by Rod Weir in Announcements A new release of HelpMaster is now available.  This release builds upon features and stability, particularly in the workflow, change management a...

    February 2019 release now available by Rod Weir in Announcements A new release of HelpMaster is now available.  This release builds upon features and stability, particularly in the workflow and web portal. F...

    RE: Job Templates get a new config option for web-based jobs by Rod Weir in Web interface, client self-service and remote access Just further to this topic....if using workflow to log a new job from a job that already contains control sets, and you are using the option to transf...

    November 2018 release now available by Rod Weir in Announcements A new release of HelpMaster is now available.  This release contains lots of fixes, performance tweaks, improved workflow capabilities, improved ...

    Quick Re-assign from an "Unassigned" skillgroup queue by Rod Weir in Using HelpMaster The upcoming November release of HelpMaster contains a small, but very handy new feature. When a job is assigned to the "Unassigned" queu...