When adding actions to a job through the web console in HM, the Time (hh:mm:ss) boxes are greyed out and I can not put in time spent. Only Cost is available.
Is this a flaw or are we meant to be able to put times in?
Thanks for your reply Suman.
We are running version 9.0 at the moment.
I have just gone into a previously added action and then was able to put the time spent in manually. I will use this as a work around until we upgrade to version 9.1
Thanks